· Application · 09/03/2026
NSEB approves NS Power's second extension request, setting September 18 deadline for feedback on Synapse draft reliability report
AI summary
- Nova Scotia Power Inc requested a further extension on September 3, 2026, citing the need for additional time to "fulsomely address" all aspects of the Synapse Energy Economics draft report on the System Reliability Five-Year Reliability Plan 2025-2029
- The Nova Scotia Energy Board approved the extension the same day, moving the deadline for participant feedback on the draft report from September 8, 2026 to Friday, September 18, 2026
- The extension applies to all parties in M12558, not solely NS Power
- The Board simultaneously amended the downstream milestone, setting the Final Report filing deadline to Monday, October 26, 2026
- The Boards Regulatory Rules Rule 7(3) filing-by-2:00-pm requirement remains in effect for all due dates
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 103447 Letter from NSPI requesting further extension
- 103448 Board letter approving further extension request