· Application · 04/28/2026
EfficiencyOne refiles NS Power Rate Model Excel attachments in M12780 after original macro-enabled files could not be opened by parties
AI summary
- Counsel Efficiencyone filed a letter (Document 101775, April 28, 2026) advising the Nova Scotia Energy Board that two Excel exhibits were being refiled at the Board's request after the originally submitted macro-enabled (.xlsm) files were inaccessible to participants.
- The refiled documents are Appendix B, Attachment 7 (E-5) — the NS Power Rate Model for the 2027-2031 Demand Side Management Preferred Resource Plan and 2026 Historical — and Attachment 8 (E-5-(i)) — the NS Power Rate Model for the 2027-2031 Alternate Scenario and 2026 Historical.
- Macros were removed from both files to ensure parties could open them; no substantive data changes were indicated.
- The spreadsheets contain transfer function and Cost Recovery cost factor analysis across thousands of rows, covering elements such as fixed costs, fuel costs, demand cost calculations, and Rate Design inputs relevant to the 2027-2031 DSM plan proceeding.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- E-5 Appendix B - Attachment 7 - NS Power Rate Model - 2027-2031 Preferred Plan and 2026 Historical - REFILED Excel
- E-5-(i) Appendix B - Attachment 8 - NS Power Rate Model - 2027-2031 Alternate Scenario and 2026 Historical - REFILED Excel
- 101775 Letter E1 re: Refiled excels