NSUARB Staff issued three information requests to Nova Scotia Power regarding the CI# 33562 FAC Land Registration Act capital work order, seeking reconciliation of property migration numbers and cost justification.
AI summary
- Board Staff IR-1 asks NSPI to provide actual activation and completion dates for the predecessor Land Registration Act project (CI# 25262) and to elaborate on $17,000 incurred to date, as referenced in IR-GP21(b).
- IR-2 requests NSPI reconcile the discrepancy between the ~1,500 freehold and property interests cited in a March 2009 IR response (CI# 33562) and the 612 property identification numbers stated in the current approval request (CI# 33562), and explain the forecasted increase in average per-parcel migration cost above the previously estimated $1,000.
- IR-3 asks NSPI to provide the basis for the $566,668 forecasted cost attributed to 'Royalties, Easements, App' within the $1,899,162 ACE plan work order.
- Responses to all three information requests are due January 7, 2011, directed to NSPI Manager of Capital Lee Thomson-Lutz and coordinated by Board Senior Analyst Branko Zatezalo, P.Eng.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →