AI-generated summary
· Ir · unknown
Nova Scotia Power filed redacted IR responses detailing property migration scope, costs, and confidentiality claims in the Land Registration Act capital item proceeding (CI# 33562).
AI summary
- NSPI confirmed that CI# 25262 (activated June 2004, completed November 2010) migrated 1,121 hydro properties into Nova Scotia's new land registry system at a total cost of $935,002.94, with the largest expenditure category being Other Goods & Services at $659,568 (IR-1).
- CI# 33562, the subject of this proceeding with an ACE amount of $1,892,331, targets 612 of an estimated 1,500 remaining freehold and property interests (vacant lands) over a five-year period (2010–2014), with approximately 888 further properties deferred to a future application; NSPI acknowledged an oversight in the original filing description that overstated the scope (IR-2).
- The $566,668 forecasted for 'Royalties, Easements, App' includes $51,102 in land registration fees for 612 PIDs at $83.50 each, $32,566 for additional document registrations, and $483,000 in surveying, drawing, and copyright fees, the latter of which was redacted in the non-confidential version (IR-3).
- NSPI asserted confidentiality over supplier pricing details in IR-3, arguing that disclosure would undermine competitive procurement and ultimately harm ratepayers, as customer rates are cost-based.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- N-2 Redacted Responses to Information Requests 1/7/2011