Nova Scotia Power filed a $603,418 capital work order application for PA damper replacement at Trenton Unit 6, submitted pursuant to section 35 with zero dollars spent to date.

M03333 · CI# 39471 - P-510 - NSPI WO - TRE6 - U&U PA Damper Replacement - $603,418Zero dollars spent to date
AI summary
  • Nova Scotia Power Incorporated filed Work Order CI# 39471 (Exhibit N-1) seeking approval for replacement of primary air (PA) dampers at Trenton Unit 6, with a total project estimate of $603,418 — up from an original cost estimate of $430,000.
  • The scope covers replacement of the 6A & 6B hot air control dampers, primary air shutoff (PASO) dampers, capacity dampers, and adjacent ductwork serving the unit's coal pulverizers.
  • The justification cites a confirmed inspection finding that existing pneumatic drives rendered PA dampers difficult to activate; temporary repairs returned the unit to service but full replacement was deemed necessary for safe and efficient operation, including NFPA compliance for PASO damper shutoff capability.
  • The project was timed to coincide with the 2010 planned shutdown (estimated in-service date May 15, 2010; final cost date May 30, 2010) to avoid costlier unplanned outages; the largest cost components are contracts ($363,436) and materials ($166,245).
  • At the time of filing, no funds had been spent against the project budget.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • N-1 Non-Confidential Work Order 6/29/2010 exhibits