· Decision · 08/12/2010
NSUARB approved Nova Scotia Power's final cost of $4,106,621 for the Trenton Unit 6 Low NOx Combustion Firing System, a $1,501,019 reduction from the originally approved amount.
AI summary
- The Board approved Nova Scotia Power Inc's request (letter dated July 30, 2010) for final cost sign-off on Work Order CI# 28866, the TRE Unit #6 Low NOx Combustion Firing System, at $4,106,621 (Doc. 180273).
- The project was originally approved on October 31, 2007 at $5,607,640; the final cost represents a variance of ($1,501,019), or approximately 26.8% below the original budget.
- The Board noted that materials and contracts came in $1,408,759 below estimate, with labour and overhead costs also lower than forecast, driving the overall savings.
- Approval was issued by Board Member Kulvinder S. Dhillon, P. Eng., on August 12, 2010.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 04987 Board Decision Letter
- 04987 Board Decision Letter