Nova Scotia Power filed a capital work order application seeking UARB approval for $1,506,414 in 2010 substation cutout and insulator replacements across 28 transmission substations.

M03509 · CI# 38878 - P-128.10 - NSPI WO - 2010 Substation Cutout and Insulator Replacements - $1,506,414
AI summary
  • Nova Scotia Power filed CI# 38878 (Exhibit N-1, dated September 2, 2010) requesting approval for a $1,506,414 Capital Expenditures project to replace failing porcelain cutouts at 28 transmission substations province-wide, slightly exceeding the budget estimate of $1,500,961 primarily due to increased capitalized interest (+$6,045).
  • The justification is reliability-driven: porcelain cutouts develop hairline cracks from moisture ingress, causing failures that trigger System Reliability outages affecting multiple feeders and large numbers of customers simultaneously; NSPI acknowledged no formal studies underpin the program — it is driven by observed failure rates.
  • The 28 targeted substations (including Sackville/90H serving ~9,969 customers, Keltic Dr./11S serving ~10,152, and Willow Lane/15N serving ~9,722) span multiple divisions; however, NSPI stated it does not separately track cutout-specific outage data under Canadian Electrical Association codes, limiting granular performance reporting.
  • Cost breakdown per IR-T9 response: Contracts $900,000 (affiliate forces), Materials $304,000, Overhead $250,752, Interest $22,254, and Labour $30,000; the contract rate per hour was redacted from the public filing.
  • Work is scheduled for completion within 2010 (start October, in-service November, close December), with the majority executed by an Affiliate Transactions affiliate entity.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • N-1 Redacted Work Order 9/2/2010 exhibits