Nova Scotia Power filed a work order application seeking UARB approval for $473,599 in capital expenditures to replace deteriorated 25kV underground cables on circuits 1H-403 and 1H-405 in downtown Halifax, the first phase of a five-year replacement program.

M03512 · CI# 38903 - P-128.10 - NSPI WO - Halifax UG Cable Replacement - $473,599
AI summary
  • Nova Scotia Power filed CI# 38903 (Project D301) for replacement of approximately 2.8 km of 25kV underground cable between the Water Street Substation and Scotia Square on feeders 1H-403 and 1H-405, at a project estimate of $473,599 — below the ACE 2010 budget of $592,567, with variance primarily attributable to lower NSPI labour and overhead than originally estimated (Variance Summary, Approval Sheet).
  • Justification for the project is the deterioration of cables installed in the early 1970s, which have reached their estimated 35-year useful life; the supporting Distribution Capital Investment Report (drafted October 5, 2009) assessed all four aging downtown feeders (1H-403, 1H-405, 1H-419, 1H-431) covering approximately 18,620 m of cable over 30 years old (Section 1.0, 5.1).
  • The five-year replacement program sequences radial sections first (2010–2012) followed by loops and ties (2013–2014), with 2010 work also including removal of 1,000 m of old PILC cable on Granville Street; all work is to be performed by internal NSPI forces except traffic control (IR-D10 Response, Section 8.0).
  • The planning report evaluated cable replacement against cable injection options, concluding via Replacement Chain Method (at 8% discount rate) that full replacement ($1,238,000 NPV over 40 years) was cost-competitive with TCI injection ($1,265,197 over two 20-year cycles) and more costly than Novinium injection ($823,314 with 40-year warranty), while noting injection risks including non-standard hardware and warranty coverage gaps (Section 7.0, Table 7.3).
  • The 2010 cost breakdown is: Materials $274,320 (primarily underground cable); Labour $102,654; Administrative Overheads and Interest $97,743; Contracts $26,181; Salvage credit $(27,500); Other $201 (Approval Sheet cost breakdown).

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • N-1 Redacted Work Order 9/2/2010 exhibits