Nova Scotia Power filed a capital work order application seeking UARB approval for $648,220 to refurbish the turbine governor on Trenton Generating Station Unit 5 following an emergency outage.
AI summary
- Nova Scotia Power Incorporated submitted CI #39663 (dated July 30, 2010; signed August 25, 2010) to the Nova Scotia Utility And Review Board under s. 35, requesting approval for a $648,220 capital expenditure to refurbish the turbine governor on Trenton Unit 5 (cost centre 340), with the project estimate exceeding the original $350,000 budget authorization.
- An unplanned outage in March 2010 revealed that the worm and worm wheel on the cross shaft had failed due to insufficient backlash and tooth clearance resulting from normal wear; a Siemens emergency outage report (Report No. 10-844, Draft) documented five key repair items including worm/wheel replacement, main and auxiliary governor refurbishment, reheat emergency stop valve seat lapping, main thrust bearing inspection, and oil system flush to clear brass particulate contamination.
- The total project cost estimate of $648,219.99 (Exhibit N-1) comprised $121,000 in materials, $128,000 in plant labour, $314,200 in contractor labour, $24,000 in engineering and project management, and $59,020 in indirect costs (interest and administrative overhead allocations); a separate retirement cost of $350,000 was also identified.
- The economic justification analysis ranked governor refurbishment (Alternative A) as the sole viable option, yielding a net present value of $3,163,190, an IRR of 67.34%, and a discounted payback of 2.7 years at a 6.55% after-tax WACC, with the primary benefit being avoidance of replacement energy costs while the unit remained offline.
- Siemens' draft report recommended additional follow-up work at the earliest opportunity, including rebabbitting the #1 bearing, replacing governor bushes, installing new trip plunger sleeves, and inspecting all other bearings at the next scheduled outage.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- N-1 Redacted Work Order 9/2/2010