· Application · 05/17/2019
Nova Scotia Power notified the Board of pre-IRP workshops planned for May–July 2019 ahead of its mid-2020 Integrated Resource Plan completion deadline.
AI summary
- NS Power confirmed it is on track to complete four pre-IRP deliverables—including a loss of load expectation (LOLE) study, resource option cost/performance assumptions, demand response assumptions, and a transmission study for increased renewables—by July 31, 2019, as directed by the Board's October 5, 2018 letter.
- The letter references underlying analytical work from the Synapse Compliance Generation Utilization and Optimization report and the Bates White audit of the Fuel Adjustment Mechanism for 2016–2017 as the basis for the pre-IRP scope.
- Nova Scotia Power announced an initial Webex conference on May 24, 2019, followed by two additional workshops in June and July 2019, to brief interested parties on pre-IRP deliverables and key planning environment changes.
- The Company requested the Board circulate the notice to relevant distribution lists and asked interested parties to confirm participation by contacting [email protected].
- The broader Integrated Resource Plan IRP process, including assumptions development and modeling (covering Synapse recommendations 6, 8, and 9), is expected to proceed after the pre-IRP analyses are finalized.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 77668 Letter from NSPI re pre-IRP workshops