Nova Scotia Power notified the NSUARB of a one-week delay in circulating its Draft IRP Findings, Roadmap & Action Plan, rescheduling stakeholder distribution to September 2, 2020.

M08929 · P-884 - Nova Scotia Power Inc. (NSPI) - Integrated Resource Planning (IRP) and M08059--Generation Utilization and Optimization
AI summary
  • NS Power informed the Board that its Draft Findings, Roadmap & Action Plan — previously scheduled for August 26, 2020 — will be issued to stakeholders on September 2, 2020, citing ongoing modelling work with consultant E3 Energy And Environmental Economics (E3).
  • The Board had previously approved an extension of the Integrated Resource Plan IRP Final Report deadline from September 30 to October 30, 2020; all remaining milestones beyond the draft circulation date remain unchanged.
  • NS Power extended the stakeholder comment period on the Draft Findings to September 18, 2020, providing two additional days over the originally allotted time.
  • Regular coordination meetings with Board staff and Board consultants Synapse Energy Economics and Bates White are ongoing to address additional modelling and deliverable requirements.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • 81723 Letter from NSPI re. update on filing final IRP Report other_documents