NSEB approves Nova Scotia Power's request to extend IRP Final Report filing deadline to November 27, 2020

M08929 · P-884 - Nova Scotia Power Inc. (NSPI) - Integrated Resource Planning (IRP) and M08059--Generation Utilization and Optimization
AI summary
  • NS Power requested a further extension of the Integrated Resource Plan IRP Final Report filing deadline from October 30, 2020 to November 27, 2020, citing the need to process stakeholder feedback on its Draft IRP Findings, Action Plan and Roadmap (Exhibit 82123).
  • NS Power confirmed it had issued draft findings to stakeholders, hosted a stakeholder workshop, received feedback, and was circulating the draft IRP Report as of October 30, 2020 (Exhibit 82123).
  • The approved milestone schedule sets stakeholder comments on the Draft IRP Report due November 13, 2020, and the Final IRP Report to be filed with the NSUARB by November 27, 2020 (Exhibit 82126).
  • The Board panel approving the extension consists of Chair Peter W. Gurnham, Q.C., Vice Chair Roland A. Deveau, Q.C., and Member Steven M. Murphy, MBA, P.Eng. (Exhibit 82126).

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • 82123 Letter from NSPI re. extension request other_documents
  • 82126 Board Letter re. extension request other_documents