NSEB approves Nova Scotia Power's request to extend Evergreen IRP reply submission deadline to October 17, 2023
AI summary
- Nova Scotia Power Incorporated filed its Evergreen IRP – Updated Action Plan and Roadmap – 2023 on August 8, 2023, initiating a structured comment proceeding established by the Nova Scotia Utility And Review Board on August 31, 2023.
- Board counsel consultants Synapse and Bates White filed submissions on September 8, 2023, followed by six participant submissions on September 26, 2023, including from Grid Strategies (on behalf of the Consumer Advocate), the Small Business Advocate, EfficiencyOne, Eastward Energy, Port Hawkesbury Paper, and Nova Scotia Department of Natural Resources and Renewables.
- NS Power requested a one-week extension — from October 10 to October 17, 2023 — citing the need to fully address the volume and scope of consultant and participant comments and recommendations.
- The Board approved the extension request on October 10, 2023, via letter from Regulatory Affairs Officer/Clerk Crystal Henwood (Document 308281).
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 91526 Letter from NSPI requesting extension to file Reply
- 91530 Board letter approving extension