Nova Scotia Power's Dispatch Study Action Plan implementation delayed to June 2026 due to interface testing issues
AI summary
- NS Power submitted its Q1 2026 quarterly update on the Dispatch Study Action Plan on March 27, 2026
- The Board accepted the filing on April 7, 2026
- Implementation has been delayed from the previously expected March 2026 deadline to June 2026
- NS Power reported that "significant issues were encountered during interface testing" causing the delay
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- 101481 Board Letter re: Accepted as filed