AI-generated summary · Decision · 06/26/2026

NSEB approved NS Power's RTU Replacements Phase 6 with a 13% labour hour reduction, directing resubmission of capital approval form CI C0051815 within two weeks.

M12550 · To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
AI summary
  • The Board ordered a 13% reduction in labour hours from NS Power's revised December 2025 estimate for CI C0051815 (RTU Replacements Phase 6, $5,959,515), splitting the difference between the independent consultant Midgard's recommended 30% cut and NS Power's position that no reduction was warranted; NS Power must resubmit the capital approval form within two weeks.
  • Independent consultant Midgard (Exhibit N-3) found a 33% variance between NS Power's filed labour estimate and an allocation derived from Phase 6 technical documents (1,291 vs. ~1,939 hours per RTU), citing a 228% increase in overtime labour versus Phase 5 and the absence of task-level traceability as key concerns.
  • The Board expressed pointed concerns about NS Power's initial cost submission, noting that a ~$900,000 reduction triggered by completing just two of 14 sites — partly attributable to duplicated line items in the original estimate — should have been avoidable given the utility's six-phase experience with RTU replacements.
  • A cybersecurity incident limiting access to historical baseline data was acknowledged as a complicating factor, but the Board found it did not excuse the insufficient justification provided in response to Undertaking U-8 in the underlying 2025 ACE Plan proceeding (M12012).
  • The Board reaffirmed that NS Power must complete the project safely regardless of the approved budget, that cost overruns may be addressed through an after-the-fact ATO filing, and directed NS Power to address overall project efficiency — including sequencing from lower- to higher-complexity sites — in any future RTU phase submissions.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →