Nova Scotia Power filed an Authorization to Overspend application for the L5541 Water Crossing Upgrades transmission project, seeking $2,265,295 against an approved budget of $1,047,074 — a $1,218,221 overrun driven by significantly higher-than-estimated steel monopole and foundation costs.

M12960 · Nova Scotia Power Inc. - CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 (ATO)
AI summary
  • Nova Scotia Power filed CI C0052654 on July 13, 2026, requesting an Regulatory Approval Processes Authorization to Overspend (ATO) of $1,218,221 (116% above the 2023 ACE Plan approved amount of $1,047,074), bringing the total project estimate to $2,265,295 for replacement of deteriorated assets on 7 structures at two water crossings on the 69kV L5541 transmission line near Deep Brook.
  • The primary driver of the overrun is sharply higher contractor costs for specialized steel monopole foundations and towers: original budget assumed $100,000 combined for both, while final engineering produced contractor estimates of $1,293,667 for foundations and $404,000 for steel towers — NSP acknowledges it lacked historical experience with these foundation types and, in hindsight, should have awaited final engineering before the original submission (Reason for Variance section).
  • Capital Expenditures overrun was partially mitigated through coordination with the Mersey Wind Interconnection Project (L-6554): by implementing a shared double-circuit crossing for structures 008–011, foundation costs borne by NSP were reduced from $1,293,667 to $646,833 and steel tower costs from $404,000 to $202,000, saving approximately $848,833 compared to constructing independent crossings.
  • The project is classified as a Class 3 estimate with 81% of required deliverables complete and a 15% contingency ($208,609) applied to contract costs, covering risks including shortened outage windows, unforeseen contract cost increases, and access difficulties at the water crossing structures (Contingency Statement).
  • Contract costs constitute the largest single cost category at $1,390,730 (61% of total), with steel tower contracts alone at $990,177; Power Infrastructure asset retirement is categorized under Accounting Policy 6420, representing 0.2% of the Transmission Plant – Towers and Fixtures asset pool with an estimated 45-year asset life.

Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

What was filed

Documents filed on this day

  • N-1 CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 exhibits