AI-generated summary
· Application · 08/19/2026
IESO Nova Scotia and Nova Scotia Power file executed interim SGIP Administration Agreement with the NSEB in Matter M12524
AI summary
- IESO Nova Scotia submitted a letter dated August 18, 2026 to the NSEB advising that Ieso Nova Scotia and Nova Scotia Power have executed the interim Generator Interconnection administration agreement referenced in the Board's prior proceeding under M12524.
- The agreement formalizes the division of responsibilities under the currently Board-approved Generator Interconnection Standard Generator Interconnection Procedures (SGIP), with IESO NS assuming System Operator functions and NS Power retaining Transmission Owner functions, as detailed in Schedule A (Interim Allocation of Responsibilities).
- The agreement operates on an interim basis under the More Access To Energy Act transition framework until revised SGIP are documented, stakeholder consultation completed, and Board approval obtained for updated procedures.
- Key operational provisions address handling of existing and new interconnection applications, deposit transfers between parties, Facility Study agreements (which remain with NS Power), and a joint coordination committee for dispute resolution before escalation to the NSEB.
- The agreement was signed August 18, 2026 by Matthew Drover (VP, Strategy & Customer) for NS Power and Chris Milligan (VP, System Planning & Grid Integration) for IESO NS.
Disclaimer: This summary was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
What was filed
Documents filed on this day
- N-2 Interim Interconnection Agreement