    04690 Other documents

    Letter from the Board approving NSPI's request for an extension of filing date for its Response to Submissions 6/30/2010

    ⬇ Download original
    04690.pdf · PDF · 45.1 KB · 1 page

    No AI summary available — too little text in this document to summarize.

    Filed in: M03097 — CI# 28098 - P-128.07 - NSPI WO -  Authority to Overspend the Tufts Cove 6 Waste Heat Recovery Project - $8,699,864Approximate value for approval of $8.5 million.

    1 page
    100%
    ⬇
    In this matter
    More from this matter
    ⌕
    • N-1 Application 5/3/2010
    • N-2 NSPI (NPB) IR-1 to IR-4 7/16/2010
    • N-3 Redacted NSPI (NSUARB) IR-1 to IR-20 7/16/2010
    • N-4 Written Submission - Avon et al. 7/22/2010
    • N-5 Written Submission - NPB 7/22/2010
    • N-6 Written Submission - NSDOE 7/22/2010
    • N-7 NSPI Reply Submission 8/6/2010
    • 05796 Board Order
    • 05797 Board Decision
    • 04378 Letter to Stakeholders setting June 11, 2010 to request participation in this ATO request 5/27/2010
    • 04606 Timetable for Review Process 6/22/2010
    • 04691 Information Request IR-1 to IR-20 issued by Board Staff to NSPI 6/30/2010
    • 04698 NPB IRs to NSPI (IR-1 to IR-4) 6/30/2010
    • 05681 Submission filed by Municipal Electric Utilities of Nova Scotia Cooperative
    • 05768 Letter to NSPI identifying several issues for NSPI to address at oral hearing 9/23/2010
    • 05796 Board Order
    • 05797 Board Decision

    No matching documents.

    1 / 2 Next →
    DocketWatch — Baseline Energy Analytics Ltd.
    Disclaimer · Terms of Use · Privacy Policy
    Feedback

    Please enter some feedback.

    Your feedback helps shape DocketWatch.

    Thanks — sent ✓