This document is a Board Decision and Order from the Nova Scotia Utility and Review Board. It covers the approval of several electrical infrastructure projects by Nova Scotia Power Incorporated, including a transmission line project in Kings County, Nova Scotia, and the associated costs, following a public review process.

Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

Filed in: M03415 — NSPI CI# 38819 - $7,452,511 - 51V Tremont Circuit Breaker & Bus

2 pages