This document is a Board Decision Letter from the Nova Scotia Utility and Review Board. It covers the approval of a reduced final cost for a work order related to a Low NOx Combustion Firing System requested by Nova Scotia Power Inc., originally approved in 2007.

Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

Filed in: M03430 — CI# 28867 - P-128.10 - NSPI WO - LIN Unit#1 Low Nox Combustion Firing System $3,875,373

Filing event: DECISION on 08/12/2010 · View digest →