Board Decision Letter
05462.pdf · PDF · 73.9 KB · 1 page
AI overviewWhat this document contains
This document is a Board Decision Letter related to Matter No. 03509, which covers Nova Scotia Power Inc.'s request for regulatory approval of a 2010 ACE Plan work order involving substation cutout and insulator replacements. It outlines the approval of $1,506,414 for the project, noting the improved reliability for 135,000 customers and confirmation of the project's necessity and cost justification.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M03509 — CI# 38878 - P-128.10 - NSPI WO - 2010 Substation Cutout and Insulator Replacements - $1,506,414
Filing event: DECISION on 10/12/2010 · View digest →