This document is an NSEB approval sheet for the TUC Wharf Access Bridge Replacement project by Nova Scotia Power Incorporated. It covers the project's expenditure profile, including budget amounts and authorization details for 2024 and 2025, as well as the total estimated cost of $2,426,669 for replacing the deteriorated Tufts Cove Wharf Access Bridge.

Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →

Filed in: M12420 — Nova Scotia Power Inc. - CI C0067183 – TUC Wharf Access Bridge Replacement - $2,426,669 (U&U)

Filing event: DECISION on 11/07/2025