Board Decision Letter
99908.pdf · PDF · 376.7 KB · 3 pages
AI overviewWhat this document contains
This document is an exhibit filed as part of a decision batch in a Nova Scotia Energy Board regulatory matter. It contains a Board Decision Letter approving a $4.465 million capital expenditure by Nova Scotia Power Inc. to install underground electrical infrastructure along Robie Street in Halifax, as well as an NSEB Approval Sheet detailing the project's expenditure profile from 2025 to 2027.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M12456 — Nova Scotia Power inc. - CI C0074130 – Robie Street Underground – $4,465,119 (P&A)
Filing event: DECISION on 11/07/2025