Board Decision Letter
99799.pdf · PDF · 350.1 KB · 3 pages
AI overviewWhat this document contains
This document is a Board Decision Letter, part of a decision batch, filed in a Nova Scotia Energy Board regulatory matter. It contains information regarding the approval of final cost capital for the L7005 Replacements and Upgrades Phase 2 project, including the approved amount, reasons for the delay in completion, and expenditure profile details.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M12506 — Nova Scotia Power Inc. - CI C0041805 – L7005 Replacements and Upgrades Phase 2 – $2,910,451 (FIN)
Filing event: DECISION on 10/27/2025