Board Decision Letter
100765.pdf · PDF · 485.5 KB · 4 pages
AI overviewWhat this document contains
This document is a Board Decision Letter from the Nova Scotia Energy Board (NSEB) related to a regulatory matter. It contains the Board's approval of a capital expenditure request by NS Power for $1,025,626 to re-insulate 42 of 44 rotor poles on Big Falls Unit 6's generator, along with details regarding the project's budget and filing type.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M12508 — Nova Scotia Power - CI C0080112 – HYD Big Falls Unit 6 Rotor Re-Insulation (U&U) - $1,025,626
Filing event: DECISION on 01/30/2026