AI overviewWhat this document contains
This document is an exhibit filed in a Nova Scotia Energy Board regulatory matter, and it contains information related to capital project authorizations, budget variances, and a project to rewind the 6P mobile transformer. Topics covered include expenditure profiles, project costs, asset replacement options, budget variances, and the status of the 6P mobile substation.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M12595 — Nova Scotia Power Inc. - CI 51956 – 6P Mobile Substation Rewind U&U $635,776 (FIN)