DRO Decision d. August 22, 2026 (redacted)
H-3.pdf · PDF · 167.9 KB · 2 pages
AI overviewWhat this document contains
This document is an exhibit containing a ruling by the Dispute Resolution Officer (DRO) in a regulatory matter involving a customer dispute with Nova Scotia Power over an additional invoice for a line extension project. It covers the DRO's decision that NSP appropriately billed the customer based on Board Regulation 2.6, citing increased backhoe costs as the reason for the cost overrun, and outlines the customer's right to appeal the decision.
Disclaimer: This overview was generated by AI from the filings it describes. We take care to make it accurate, but errors are possible - and it isn't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →
Filed in: M13074 — NSPI DRO Appeal - Billing Issues - Joanna Hammersley
Filing event: APPLICATION on 09/04/2026 · View digest →