HomeMattersM03453
M03453 Closed Electricity

E-LUN-R-10 - Lunenburg Electric Utility - Request a change to the flow through formula used to calculate the NSPI Municipal Rate Class increases.IN THE MATTER OF the Application of the Town of Lunenburg on behalf of its Electric Utility for approval of a change to the flow through formula used  to calculate amendments to its Schedule of Rates for the provision of electric services to its customers to recover costs incurred as result of the rate increases granted to Nova Scotia Power Incorporated.

Filed 08/27/2010 3 documents
Hearing scheduled November 1, 2010 · Order 10/19/2010 View order →

What's happened

Filing Timeline

  • Document
    Town of Lunenburg applied to replace its two-year historical averaging formula for NSPI municipal rate pass-throughs with a forward-looking forecast-based formula.
  • 19 Oct
    Order
    NSUARB approved Lunenburg Electric Utility's amended flow-through formula for passing NSPI Municipal Rate Class increases to customers, effective November 1, 2010.

The filings themselves

Documents

Key documents 1 file
  • 59945 Board Order PDF · 10/19/2010
Exhibits 1 file
  • L-1 Application 8/27/2010 PDF
Other documents 1 file
  • 59945 Board Order PDF · 10/19/2010

What's discussed — click to drill in

Topics