Topic/Matter Intersection

Topic:"2025 Ace Plan" in M03086

Matter: CI# 34622 - P-128.10 - NSPI WO - Upgrade L-8002 - $1,648,189
2 passages 2 documents

2025 Ace Plan across all matters →

N-1Redacted Work Order 4/30/2010 1 passage
NON-CONFIDENTIAL p. p. 1
NON-CONFIDENTIAL 1 Transmission Responses 2 3 Request IR-Tll: 4 5 With respect to page 201, CI# 34622 - Upgrade L8002, 6 7 a) This project is a continuation of the work started in the 2009 ACE Plan under CI# 8 33542. Please provide an upda...

AI summary The text discusses a request for an update on a transmission project (CI# 34622) related to the 2009 ACE Plan, including budget versus actual expenditures, sufficiency of the budget, and compliance with a Board Order requiring documentation of code compliance.

N-2Redacted Responses to Information Requests 5/31/2010 1 passage
NON-CONFIDENTIAL p. p. 0
NON-CONFIDENTIAL 1 Request IR-6: 1 Request IR-8: 2 3 In its response to the ACE Plan 2010 IR-T11 (a), NSPI stated: 4 5 6 7 8 The actual work encountered in 2009 was as previously forecasted. The ACE amount for this project was $1.6 million...

AI summary NSPI explained a variance in the ACE Plan 2010 project costs due to lower material and contract costs, and stated that CI #34622 is expected to be completed on budget. The project was not fully completed in 2010 due to transmission line outage scheduling, with no additional costs identified for completing the work in two phases.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →