Matter: CI# 34602 - P-128.10 - NSPI WO - 25kV  Feeder Extension Bissett Road - $1,036,178
2 passages 1 document

2025 Ace Plan across all matters →

N-1Redacted Work Order 5/4/2010 2 passages
Cost Centre 800 - 800-Services - Admin. Budget Version - 2010 ACE Plan (New AFUDC) p. p. 1
Cost Centre 800 - 800-Services - Admin. Budget Version - 2010 ACE Plan (New AFUDC) Forecast Start 04/01/2010 Operational 07/31/2010 Final Cost 12/31/2010 2010 $1,036,177. 71 Total: $1,036,177.71 Original Cost: $115,719.95 This project is t...

AI summary The document outlines a project to construct a 25kV circuit from East Dartmouth to Eastern Passage, including upgrades and voltage conversion in the Cow Bay area, with a total forecasted cost of $1,036,177.71 for the 2010 ACE Plan.

Why do this project this way? p. p. 1
Why do this project this way? Alternatives to extending this feeder include building a 138kV transmission line and a new substation in Eastern Passage. This item was investigated in th\'l Distribution Planning Study . "Dartmouth 25kV Syste...

AI summary The document outlines alternatives to extending a feeder, including a 138kV transmission line and substation in Eastern Passage, referencing a 2008 Distribution Planning Study. The current approach is deemed the most cost-effective, executed by NSPI and an affiliate under ACE 2010 guidelines.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →