By E-mail and Courier Ms. Lee Thomson-Lutz Capital Manager Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI- Request for Approval of 2010 ACE Plan Work Order - P-128.10 CI# 38022 - 2010 Re...
AI summary The Board approves a 2010 ACE Plan Work Order for $1.4 million to install reclosers, deeming the project necessary and cost-justified.