Home2025 Ace PlanM03510Evidence
Topic/Matter Intersection

Topic:"2025 Ace Plan" in M03510

Matter: CI# 34622 - P-128.10 - NSPI WO - Upgrade L-8002 - $2,222,639
1 passage 1 document

2025 Ace Plan across all matters →

06274Board Decision Letter 1/28/2011 1 passage
NSPI Request for Approval of 2010 ACE Plan Work Order CI#34622 - L8002 Upgrade - P-128.1 0 p. p. 0
NSPI Request for Approval of 2010 ACE Plan Work Order CI#34622 - L8002 Upgrade - P-128.1 0 The Board has reviewed NSPI's application dated September 2, 2010 in which Board approval is requested for the following non-confidential 2010 ACE P...

AI summary The Board has approved NSPI's request for $2,222,693 to upgrade the L-8002 work order under the 2010 ACE Plan, as the project is necessary to meet CSA ground clearance requirements on a 345KV circuit.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →