Matter: CI# 38903 - P-128.10 - NSPI WO - Halifax UG Cable Replacement - $473,599
1 passage 1 document

2025 Ace Plan across all matters →

05461Board Decision Letter 1 passage
Bye-mail and courier p. p. 0
Bye-mail and courier Ms. Lee Thomson-Lutz Manager, Capital Nova Scotia Power Inc. 14th Floor, Barrington Tower Halifax, NS B3J 2W5 Dear Ms. Thomson-Lutz: NSPI - Request for Approval of 20; 0 ACE Plan Work Order CI# 38903 - Halifax UG Cable...

AI summary The Board approved Nova Scotia Power Inc.'s 2010 ACE Plan Work Order (CI# 38903) for $473,599 to replace 25 kV underground cables in Halifax's Downtown Area. The project was deemed necessary for the safe and continuous operation of the 25 kV system. Confidential portions of the work order were accepted as filed.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →