Topic:"2025 Ace Plan" in M03626

Matter: CI# 38943 - P-128.10 - NSPI WO - LIN1 Boiler Refurbishment - $1,653,592
3 passages 3 documents

2025 Ace Plan across all matters →

06428Board Decision Letter 2/18/2011 1 passage
The Board has reviewed Nova Scotia Power's ("NSPI") letter dated and received on October 15, 2010, requesting Board approval to overspend with respect to the following Work Order: p. p. 0
The Board has reviewed Nova Scotia Power's ("NSPI") letter dated and received on October 15, 2010, requesting Board approval to overspend with respect to the following Work Order: Approved Amount ATO Amount New Approved Amount CI# 38943 -...

AI summary Nova Scotia Power requested approval to overspend on a boiler refurbishment work order, originally approved in 2010 as part of the ACE Plan. The increase in costs is due to an expansion in the scope of work following internal boiler inspections conducted after the initial approval.

06027Information Requests issued by Board Consultants 1 passage
Section 1
NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF: AN APPLICATION by Nova Scotia Power Incorporated ("NSPI") for Approval of 2010 ACE Plan Work Order CI# 38943 - Boiler Refurbishment To...

AI summary Nova Scotia Power Incorporated has submitted an application for approval of the 2010 ACE Plan Work Order CI# 38943 - Boiler Refurbishment. The application is under review by the Nova Scotia Utility and Review Board, with responses due by January 12, 2011.

06428Board Decision Letter 2/18/2011 1 passage
The Board has reviewed Nova Scotia Power's ("NSPI") letter dated and received on October 15, 2010, requesting Board approval to overspend with respect to the following Work Order: p. p. 0
The Board has reviewed Nova Scotia Power's ("NSPI") letter dated and received on October 15, 2010, requesting Board approval to overspend with respect to the following Work Order: Approved Amount ATO Amount New Approved Amount CI# 38943 -...

AI summary Nova Scotia Power (NSPI) requested Board approval to overspend on a Work Order related to the LlN1 Boiler Refurbishment, increasing the approved amount from $501,583 to $1,658,592 due to an expanded scope of work following internal inspections after the 2010 ACE Plan approval.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →