Reliability Tie Development - In addition to the engineering study work, NS Power has developed an updated project schedule that estimates a timeline of approximately 4.5 years to complete the project from current state through commissioni...
AI summary NS Power has updated the Reliability Tie project timeline to 4.5 years, included it in the 2022 ACE Plan under C0044391, and integrated it with the Atlantic Loop. The project will continue in 2022 with design, environmental studies, and engagement with NB Power.
Coal Unit Conversions - NS Power is currently determining the least cost conversion option for which gas can be readily available. - The work to date has served to validate key IRP assumptions, indicating that coal unit conversion continue...
AI summary NS Power is evaluating the least cost option for converting coal units to gas, with current work validating the Integrated Resource Plan's assumptions that coal unit conversion remains a low-cost option for customers. One conversion has been included in the 2022 ACE Plan for submittal.