2025 Ace Plan across all matters →

E-12024 DSM Annual Progress Report 1 passage
Preamble p. p. 21
6 Numbers may not sum due to rounding. 2 7 8 Another factor, unknown at the time of development of the 2025 forecast, which could impact 9 program delivery and results in 2025, is the current economic and geopolitical uncertainty 10 associ...

AI summary Uncertainty from US tariffs may impact the delivery and results of the 2025 DSM Plan by affecting business participation and job security in Nova Scotia. E1 will report on the implementation progress in quarterly reports to the new Energy Board, with the first report due in May 2025.

E-22024 DSM Programs Evaluation Reports 1 passage
27.2.2 Peak Demand Savings p. pp. 179-180
27.2.2 Peak Demand Savings Peak demand savings correspond to the demand savings that coincide in time with the peak demand period of the electricity system. The projected electricity peak demand period in Nova Scotia is between 5 p.m. and...

AI summary Peak demand savings in Nova Scotia are calculated using a 0.283 MW/GWh ratio from Navigant's 2016-2018 DSM Plan, except for heat pumps, which use updated 2024 unitary values (0.148 W/(Btu/hr)). The Evaluator validated Navigant's method, while MHEEP's savings are tracked via appliance replacements and updated in the 2024-2025 DSM MA.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →