Section 63
f the study objectives. NS Power understands that the current estimated 23 timeline for completion of the study is Q3 2025.17 24 25 To date, NS Power has participated in meetings with Net Zero Atlantic and provincial staff in a 26 working...

AI summary The document discusses the timeline for a study related to Net Zero Atlantic, with NS Power participating in working group meetings. The study is expected to be completed in Q3 2025. The text also references the 2025 ACE Plan and load forecast reports, including comparisons of residential and commercial electric heating saturation models.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →