Topic:"2025 Ace Plan" in M12372

Matter: Nova Scotia Power Inc. - CI C0067906 – POA Boiler Refurbishment 2025 – $1,218,254
4 passages 4 documents

2025 Ace Plan across all matters →

N-1Application 1 passage
Reason for Variance p. p. 1
Reason for Variance The increase of approximately $5,000 from the 2025 ACE Plan subsequent submittal estimate of $1,213,152 is primarily due to refinement of the scope. C0067906 Location: CI# : Steam Title: POA Boiler Refurbishment 2025

AI summary The increase of approximately $5,000 from the 2025 ACE Plan subsequent submittal estimate is due to the refinement of the scope, as outlined in the POA Boiler Refurbishment 2025 under location CI# : Steam.

99230Board Decision Letter 1 passage
CI # C0067906 POA Boiler Refurbishment 2025 $1,218,254 p. pp. 0-2
CI # C0067906 POA Boiler Refurbishment 2025 $1,218,254 This capital item was included in NS Power's 2025 ACE Plan with a budget of $1,213,152, listed among the projects pending subsequent approval. In its submission, NS Power indicated tha...

AI summary NS Power proposed a $1,218,254 capital item for boiler refurbishment as part of its 2025 ACE Plan. The project aims to ensure compliance with engineering standards, prevent equipment failures, and maintain safety and operational reliability. The Board accepted the project and approved the requested funding.

98424Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
2025 ACE Plan Capital Items for Subsequent Approval p. p. 0
2025 ACE Plan Capital Items for Subsequent Approval - CI C0061003 POA LP HP IP Turbine Refurbishment $4,861,261 2025 ACE amount $4,155,131 $9,776 spent as at March 31, 2025 Partially Confidential - CI C0061005 POA Cell Capping 2025 $2,530,...

AI summary The document outlines capital items under the 2025 ACE Plan for approval, including turbine refurbishment, cell capping, and boiler refurbishment projects, with details on allocated amounts and expenditures as of March 31, 2025.

99230Board Decision Letter 1 passage
CI # C0067906 POA Boiler Refurbishment 2025 $1,218,254 p. pp. 0-2
CI # C0067906 POA Boiler Refurbishment 2025 $1,218,254 This capital item was included in NS Power's 2025 ACE Plan with a budget of $1,213,152, listed among the projects pending subsequent approval. In its submission, NS Power indicated tha...

AI summary NS Power submitted a capital item for boiler refurbishment in the 2025 ACE Plan with an increased budget of $1,218,254. The project is necessary for compliance with engineering standards and to prevent equipment failures. The Board accepted the project and approved the requested funding.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →