N-21UARB APPROVAL SHEET Replace L6513/Upgrade Line Terminals 2 passages
Section 22 p. p. 8
This project was originally forecasted as a subsequent submission in the 2014, 2015, 2016, and 2017 ACE Plans. It was referenced in the 2018 ACE Plan with an updated budget of $19,251,601. It is now being submitted for approval as part of...

AI summary The project, initially planned in multiple ACE Plans from 2014 to 2017, was referenced in the 2018 ACE Plan with an updated budget and is now being submitted for approval as part of the Company's General Rate Application. It is now complete with final costs.

Reason for Variance p. p. 8
Reason for Variance The increase of $1,135,677over the 2018 ACE Plan budget of $19,251,601 to $20,387,278 in this submission is due to the completion of subsequent additional detailed engineering and scoping. At the time of the 2018 ACE Pl...

AI summary The increase in the 2018 ACE Plan budget is attributed to additional detailed engineering, specialized contractor costs such as using a Skycrane helicopter for tower installation, and post-construction avian monitoring required by environmental regulations.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →