Home2025 Ace PlanM12419Evidence
Topic/Matter Intersection

Topic:"2025 Ace Plan" in M12419

Matter: Nova Scotia Power Inc. - CI C0030984 – IT - Cisco UCS Lifecycle - $2,088,998 (FIN)
2 passages 1 document

2025 Ace Plan across all matters →

98847Second Quarter 2025 Capital Items Letter - NSPI 2 passages
2025 ACE Plan Capital Items for Subsequent Approval p. p. 0
2025 ACE Plan Capital Items for Subsequent Approval - CI C0068655 LM6000 191-332 Life Extension $18,948,560 2025 ACE amount $6,013,454 $198,627 spent as at March 31, 2025 Partially Confidential - CI C0071528 FLISR Implementation $4,638,245...

AI summary The document outlines two capital items under the 2025 ACE Plan for subsequent approval, including a life extension project and FLISR implementation, with associated costs and expenditures as of March 31, 2025.

2025 ACE Plan Capital Item Less than $1 Million p. p. 0
2025 ACE Plan Capital Item Less than $1 Million • CI 49036 – HYD - Avon 2 Controls Upgrade - $1,073,463 2025 ACE amount $496,293 $71,306 spent as at March 31, 2025 Partially Confidential

AI summary The document outlines a capital item under the 2025 ACE Plan, specifically the Avon 2 Controls Upgrade with a total cost of $1,073,463, with $496,293 allocated under the 2025 ACE Plan and $71,306 spent as of March 31, 2025. The item is partially confidential.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →