Matter: Nova Scotia Power Inc. - CI 47751 – ECC Dynamic Line Rating Implementation - $2,148,364
4 passages 3 documents

2025 Ace Plan across all matters →

N-1Application 2 passages
Section 3 p. p. 1
This project was originally submitted in September 2024 as a P&A project for $2,079,681, and subsequently withdrawn due to additional funding bringing the total project cost to <$1M. The project was therefore included in the 2025 ACE Plan...

AI summary A project initially submitted in September 2024 as a P&A project for over $2 million was withdrawn due to additional funding bringing the total cost below $1 million. It was included in the 2025 ACE Plan as a carryover project under $1 million but is now forecasting to exceed $1 million.

Reason for Variance p. p. 2
Reason for Variance This project was submitted in September 2024 as a Planned & Advanced (P&A) project, for $2,079,681, and was subsequently withdrawn as the Company was able to secure additional NRCan funding which resulted in the total p...

AI summary The project, initially submitted as a P&A project in September 2024, was withdrawn after securing additional NRCan funding, reducing the cost below $1 million. It was listed in the 2025 ACE Plan as a carryover project. The project estimate increased from $968,222 to $2,148,364 due to the inclusion of additional sensors on the NB Import Transmission Line, which presented greater geographical and terrain challenges.

101113Board Decision Letter 1 passage
Section 8 p. p. 4
This project was originally submitted in September 2024 as a P&A project for $2,079,681, and subsequently withdrawn due to additional funding bringing the total project cost to <$1M. The project was therefore included in the 2025 ACE Plan...

AI summary A project initially submitted as a P&A project for over $2 million was withdrawn due to additional funding, leading to its inclusion in the 2025 ACE Plan as a carryover project under $1M, but now forecasts to exceed $1M. The submission was made on behalf of Nova Scotia Power Incorporated and approved by the Nova Scotia Energy Board.

101113Board Decision Letter 1 passage
Section 8 p. p. 4
This project was originally submitted in September 2024 as a P&A project for $2,079,681, and subsequently withdrawn due to additional funding bringing the total project cost to <$1M. The project was therefore included in the 2025 ACE Plan...

AI summary A project initially submitted as a P&A project for over $2 million was withdrawn due to additional funding reducing the total cost to under $1 million. It was later included in the 2025 ACE Plan as a carryover project but is now forecasting to exceed $1 million again.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →