Home2025 Ace PlanM12600Evidence
Topic/Matter Intersection

Topic:"2025 Ace Plan" in M12600

Matter: Nova Scotia Power - Cybersecurity Accountability IN THE MATTER OF AN INQUIRY about the impact of the cyber incident on NOVA SCOTIA POWER INCORPORATED’s collection and retention of customer information, customer service and communications, billing processes and regulatory matters
10 passages 9 documents

2025 Ace Plan across all matters →

N-3Incident Report - Redacted (N-3 from M12273) 1 passage
NS Power Cyber Incident Report Appendix B Page 1 of 7 p. p. 44
NS Power Cyber Incident Report Appendix B Page 1 of 7 Affected Regulatory Matters Report 2 - October 1 Report 3 - November 3 Report 4 - December 1 Latest update Forecast Restoration of Normal Activities Capital and Ace Plan l

AI summary This table lists affected regulatory matters related to an NS Power cyber incident, with dates and statuses of reports. The 'Capital and Ace Plan' is mentioned as one of the affected matters.

100853NS Power's Monthly Update #2 (M12273) 1 passage
Capital Budgeting/Finance Data p. p. 5
Capital Budgeting/Finance Data In general, capital budgeting and finance data has been affected by the Incident. For example, detailed 2025 ACE Plan budget data by CI is unavailable, resulting in an inability to produce detailed variance a...

AI summary The Incident has impacted NS Power's capital budgeting and finance data, with detailed 2025 ACE Plan data unavailable and capital asset accounting systems offline. NS Power has created spreadsheets for business continuity, and this is not expected to affect customers.

100855NS Power's Monthly Update #4 (M12273) 2 passages
Capital and ACE Plan p. p. 3
Capital and ACE Plan

AI summary The text introduces the 'Capital and ACE Plan,' which likely relates to capital expenditures and the 2025 ACE Plan, indicating a focus on energy efficiency and capacity management strategies.

Capital Budgeting/Finance Data p. p. 3
Capital Budgeting/Finance Data As noted in the Second Monthly Update Report, capital budgeting and finance data was affected by the Incident, including detailed 2025 ACE Plan budget data by CI being unavailable, resulting in an inability t...

AI summary The Incident impacted capital budgeting and finance data, including the unavailability of 2025 ACE Plan budget data. NS Power used spreadsheets to maintain business continuity while PowerPlan was unavailable, allowing for continued financial reporting and the development of the 2026 ACE Plan.

100856NS Power's Monthly Update #5 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Capital and Ace Plan CapitalBudgeting/Finance Da...

AI summary Several projects have had their completion timelines adjusted, with updates on their status and expected submission to the NSEB. The CIS Replacement Project is now included in the 2026 ACE Plan, and full PowerPlan restoration is expected in Q2 2026.

101156NSPI Monthly Update Report #6 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 5
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale C apital and Ace Plan · I CapitalBudgeting/Finan...

AI summary Several projects have experienced adjustments to their completion timelines. The Capital and Ace Plan, CIS Replacement Project, and NS–NB Reliability Intertie Project are among those affected. Updates include submission timelines, regulatory approvals, and transfers of modelling responsibilities.

101623NSPI Monthly Update Report #7 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Rates-Related Matters Capital and Ace Plan Capit...

AI summary The document outlines adjustments to project timelines related to capital budgeting, finance data, and the CIS Replacement Project. The CIS project is expected to be submitted to the NSEB in 2026 as part of the 2026 ACE Plan.

102002NSPI Monthly Update Report #8 (M12273) 1 passage
Cybersecurity Incident - Monthly Update 8 Attachment 2 Page 1 of 5 p. p. 5
Cybersecurity Incident - Monthly Update 8 Attachment 2 Page 1 of 5 Affected Regulatory Matters Report 2 - October 1 Report 3 - November 3 Report 4 - December 1 Report 5 - February 4 Report 6 - March 4 Report 7 - March 31 Report 8 - May 11...

AI summary This document provides an update on cybersecurity incident-related regulatory matters, including the Capital and Ace Plan, CIS Replacement Project, and NS – NB Reliability Intertie Project. It outlines the status of these matters, including updates to the Capital Budgeting/Finance Data and the approval of the Reliability Tie project by the NSEB.

102711NSPI Monthly Update Report #10 (M12273) 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 5
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Affected Regulatory Matters Report 2 - October 1...

AI summary The document outlines adjustments to the completion timelines of various projects under affected regulatory matters, including the Capital and Ace Plan, with updates provided for different reports and a forecast for the restoration of normal activities.

20260818-1Hearing Transcript — 08/18/2026 (Chris Lanteigne, Lia MacDonald, Glen MacLeod, Blake Williams) 1 passage
NOVA SCOTIA POWER PANEL 271 Cr-ex, (Rudderham)
NOVA SCOTIA POWER PANEL 271 Cr-ex, (Rudderham) 1 consistent with the rebuttal evidence. 2 Yeah, and I'm asking if any of Q. 3 those concerns have been realized to date or do you have 4 any indication 5 (Williams) Not to my knowledge. A. 6...

AI summary The discussion focuses on the potential impacts of delaying capital projects, including increased costs due to inflation and remobilization, but also the possibility of reduced costs for customers. The conversation references the 2026 ACE Plan proceeding and the delay or cancellation of approximately 60 projects in 2025.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →