Matter: Nova Scotia Power Inc. - 2025 Annual Performance Standards Report
7 passages 4 documents

2025 Ace Plan across all matters →

N-12025 Report 3 passages
Section 24
now under way for 22 3 additional devices for substations in 2026. Grid Modernization upgrades such as these are 4 proven methods to decrease the duration of outages for customers. 5 Nova Scotia Power is committed to meeting the establishe...

AI summary Nova Scotia Power is investing in grid modernization to improve reliability and reduce outages, targeting a 20% reduction in SAIDI by 2029 and enhancing resilience against climate change. The Five-Year Reliability Plan, detailed in the 2025 and 2026 ACE Plans, focuses on operational improvements and targeted investments to meet performance standards.

Section 66
was 1.15 percent, consistent with performance over the past years. 5 6 Supporting documentation, including a monthly breakdown of performance against the target, is 7 contained in Appendix G. 8 DATE FILED: March 31, 2026 Page 37 of 115 202...

AI summary The 2025 Annual Performance Standards Report indicates a 1.15% performance metric, consistent with prior years. Supporting documentation, including monthly performance breakdowns against targets, is provided in Appendix G.

Section 94
tomer Support Roadshow - Inverness December-25 Elected Official Meeting June-25 Customer Support Roadshow - Pictou December-25 Elected Official Meeting 1 2 NS Power is committed to meeting and listening to customers and stakeholders as the...

AI summary NS Power emphasizes customer engagement through roadshows and meetings, aligning with the Five-Year Reliability Plan and 2026 ACE Plan. Climate change impacts, including 93 hours of 80+ km/h winds in 2025, are addressed through infrastructure resilience improvements and updated pole standards, reducing storm-related disruptions.

N-3NSPI (IG) RIRs 1-10 2 passages
Section 17
2025 Annual Performance Standards Report (NSEB M12784) NSPI Responses to Industrial Group Information Requests NON-CONFIDENTIAL 1 (b) N/A. For clarification, the annual tree contact outages shown in Figure 29 do not include 2 the 40 percen...

AI summary NSPI clarifies that annual tree contact outages exclude a 40% weather adjustment factor, estimating it via technician feedback. Outage reductions in 2025 resulted from favorable weather and $45M in vegetation management investments. NSPI emphasizes ongoing reliability improvements through the Five-Year Reliability Plan.

Section 23
ance in 2025 was 24 largely attributable to the third factor, the restoration time. In particular several large customer 25 count events with challenging restorations were responsible for a large fraction of overall CHI. 26 The largest 5 e...

AI summary The 2025 CHI was driven by prolonged restoration times from complex outages, with top equipment failure events accounting for over 55% of customer interruption hours. NSPI attributes increased conductor failures to infrastructure stress from high wind hours, not direct weather correlation, as noted in the 2026 ACE Plan. Weather impacts were minimal compared to equipment-related causes.

N-4NSPI (NSEB) RIRs 1-33 1 passage
Section 36
coded as Failed Equipment 13 for years 2020 to 2025. 14 Year Events 2020 3,530 2021 3,083 2022 2,942 Date Filed: May 29, 2026 NSPI (NSEB) IR-8 Page 3 of 4 2025 Annual Performance Standards Report (NSEB M12784) NSPI Responses to NSEB Inform...

AI summary The 2025 Annual Performance Standards Report (NSEB M12784) details NSPI's responses to NSEB information requests, including corrected data on equipment failure rates (18% erroneously stated, corrected to 14%) and references to the 2026 ACE Plan (M12619). Failure events declined from 3,530 in 2020 to 2,091 in 2025.

101891IG (NSPI) IR 1 to 10 1 passage
Section 4
ategories) to changes in 5 SAIDI and/or SAIFI. If so, please describe the methodology, inputs, 6 assumptions, and results, and provide supporting materials. 7 (c) Please provide the calculations and supporting data underlying the 8 reporte...

AI summary The text requests NSPI to clarify methodologies for calculating reliability metrics (SAIDI/SAIFI), verify data alignment with the 2026 ACE Plan, and explain assumptions about outage attributions (e.g., 40% adverse weather factor). It also seeks validation of the 40% allocator's basis and source.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →