Reason for Variance The increase of $1,145,722 from the 2026 ACE Plan subsequent submittal estimate of $2,457,629 is primarily due to an increase in the number of structures requiring pole and other transmission asset replacements and upgr...
AI summary The increase of $1,145,722 in the 2026 ACE Plan is due to more structures requiring pole and transmission asset replacements and upgrades, from 41 to 52 structures. Updated work procedures for live line conditions on 138 kV lines required a revision of existing CU rates, contributing to the increased project spend.