Reason for Variance The decrease of $344,651 from the 2026 ACE Plan subsequent submittal estimate of $1,353,592 is due to decreased abutment scope requirements. Core sampling during conceptual design revealed existing abutment structural i...
AI summary The $344,651 reduction in the 2026 ACE Plan estimate stems from reduced abutment scope requirements, as core sampling confirmed existing structural integrity at lower speeds on the track segment.