Matter: Nova Scotia Power Inc. - CI C0069166 - POT Turbine Valve Refurbishment - $1,544,021 2025 ACE Plan Capital Items for Subsequent Approval: CI C0069166 - POT Turbine Valve Refurbishment - $1,544,021 2025 ACE amount $2,872,598 $1,544,021 spent as at March 31, 2026 Partially Confidential
1 passage 1 document

2025 Ace Plan across all matters →

N-1CI C0069166 - POT Turbine Valve Refurbishment - Report - Redacted 1 passage
Reason for Variance p. p. 11
Reason for Variance The decrease of $1,328,577 from the 2025 ACE Plan subsequent submittal estimate is primarily due to the inspected condition of the valves requiring fewer part replacements than originally anticipated and therefore reduc...

AI summary The decrease of $1,328,577 from the 2025 ACE Plan subsequent submittal estimate is primarily due to the inspected condition of the valves requiring fewer part replacements than originally anticipated and therefore reducing material cost.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →