Matter: Nova Scotia Independent Energy System Operator (IESO Nova Scotia) - 10-Year System Outlook Report for 2026
5 passages 3 documents

2025 Ace Plan across all matters →

N-4IESO (NSEB) RIR 1 to 19 2 passages
1 Request IR – 19 p. p. 14
1 Request IR – 19 - 2 Referencing the Transmission Development Project List and Table 9, pdf page 26, IESO Nova - 3 Scotia stated: 6 7 8 9 10 11 12 14 15 16 - 4 Table 9 below lists the transmission system development projects identified by...

AI summary The document requests an explanation of the analysis behind a list of transmission system development projects identified by IESO Nova Scotia, whether these projects were included in NS Power's ACE Plan, details about the terminal points and substations for each project, and the current status of each project.

Section 47 p. p. 14
18 19 20 21 22 23 b) IESO Nova Scotia has not cross-checked the list of transmission projects in the 2026 10 Year System Outlook report with NS Power's 2026 ACE Plan. IESO Nova Scotia notes that many projects in this list are in future yea...

AI summary The IESO Nova Scotia has not verified the list of transmission projects in the 2026 10 Year System Outlook report against NS Power's 2026 ACE Plan, noting that many projects are in future years and may not be reflected until later.

103637CA (IESO) IR 1 to 9 2 passages
Request IR-7:
Request IR-7: Reference : Exh. N-1, Table 9, and NS Power's 2026 ACE Plan. The 2026 ACE Plan indicates a $13 million budget for the Michelin DVR Phase project, "for the supply, install and integration of an additional 5MVA of Dynamic Volta...

AI summary The text references the 2026 ACE Plan and a $13 million budget for the Michelin DVR Phase project, which is not included in Table 9. It asks for an explanation of why the project is excluded and IESO-NS's perspective on its significance.

Request IR-9:
Request IR-9: Reference : Exh. N-1, Table 9, and NS Power's 2026 ACE Plan. - a) Please explain IESO-NS's role in development, review, and approval of NS Power transmission projects in its ACE Plan. - b) If IESO-NS has taken any position ot...

AI summary Request IR-9 asks IESO-NS to explain its role in the development, review, and approval of NS Power's transmission projects in the 2026 ACE Plan, and to discuss any positions it has taken other than full, ongoing support for these projects.

104080Submissions - CA 1 passage
A. Scope of the Report p. p. 1
f transmission projects that IESO NS must consider when optimizing customer investments in forward-looking system planning. This lack of coordination could negatively impact system planning generally. In its 2026 ACE Plan Decision, the Boa...

AI summary The document highlights a lack of coordination between NS Power, IESO NS, and the Province in planning for decarbonization and transmission projects, which could impact system reliability and the achievement of 2030 targets. The Board emphasized the need for closer collaboration, but IESO NS has not yet responded to this directive.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →