Home2025 Ace PlanM12960Evidence
Topic/Matter Intersection

Topic:"2025 Ace Plan" in M12960

Matter: Nova Scotia Power Inc. - CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 (ATO)
2 passages 2 documents

2025 Ace Plan across all matters →

N-1CI C0052654 – L5541 Water Crossing Upgrades - $2,265,295 1 passage
Reason for Variance p. p. 1
Reason for Variance The increase of $1,218,221 from the 2023 ACE Plan approved amount is due to higher costs of steel monopoles and foundations than originally budgeted in 2023. Updated engineering for the crossing design identified signif...

AI summary The increase of $1,218,221 in the 2023 ACE Plan is due to higher-than-budgeted costs for steel monopoles and foundations. NS Power coordinated with the Mersey Wind Interconnection Project to share costs, reducing the total increase to $848,833 by implementing a shared double-circuit crossing.

102745Letter NSPI re: Capital Items Filed Outside the Quarter Package 1 passage
Authorization to Overspend (ATO) Capital Item(s) p. p. 0
Authorization to Overspend (ATO) Capital Item(s) - CI C0052654 L5541 Water Crossing Upgrades $2,265,295 Original approval received in the 2023 ACE Plan for $1,047,074 ATO amount $1,218,221 $43,635 spent as at March 31, 2026 Non-Confidentia...

AI summary The document outlines three capital projects that have been authorized to overspend (ATO) under the 2023, 2024, and 2025 ACE Plans. Each project includes original approval amounts, ATO amounts, and current spending as of March 31, 2026. Progress on each project is also noted.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →