1 risks or failures that happen each year. Due to these changes, several other p. p. 72
NON-CONFIDENTIAL 1 risks or failures that happen each year. Due to these changes, several other 2 transformers were replaced in their place due to increased risk or failures. 3 4 (iv) The program submitted as part of the Five-Year Reliabil...

AI summary The text discusses the replacement of transformers due to increased risks and failures, and references the 2025 ACE Plan and 2026 ACE Plan for details on substation capital work and completed projects. It also mentions a request and response regarding the inclusion of new substation investments in the Five-Year Reliability Plan.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →