1 TABLE OF CONTENTS 2 3 1.0 EXECUTIVE SUMMARY ................................................................................................ 7 4 2.0 2026 ACE PLAN STRUCTURE ...................................................................
AI summary The document outlines the structure and details of the 2026 Annual Capital Expenditure (ACE) Plan, including stakeholder engagement, deferred or cancelled capital items from the 2025 ACE Plan, and a summary of expenditures and capital items for the 2026 ACE Plan. It also covers generation-related capital spending.
next depreciation study with the Board prior to filing the 2026 ACE plan, the Board expects 22 the Company to provide an update on the activities it conducted since the filing of the 2025 23 ACE Plan related to evaluating and costing the M...
AI summary The NSEB requires NS Power to provide an update on activities related to the Mersey Hydro System decommissioning and partial decommissioning options since the 2025 ACE Plan was filed, and to include cost estimates for preliminary engineering, stakeholder engagement, and environmental studies in the 2026 ACE Plan.
1 engineering design costs, and procurement costs, in its Mersey system update in the 2026 2 ACE Plan. These cost estimates are also to be included in NS Power’s filing of its NPV 3 analysis comparing the Mersey Redevelopment Project to th...
AI summary The NSEB directs NS Power to include engineering, procurement, and design costs in its 2026 ACE Plan and NPV analysis of the Mersey Redevelopment Project. It also mandates a quality control step in the Project Delivery Model (PDM) and requires NS Power to submit capital expenditures over $1 million for Board approval.
he Company’s decisions related to Date: December 12, 2025 Page 29 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (Attachments Only) 1 project deferrals to ensure risks are being appropriately managed...
AI summary The 2026 Annual Capital Expenditure (ACE) Plan outlines NS Power's proposed capital investments totaling approximately $256.3 million. It includes routine capital expenditures and 20 projects, with some items not requiring NSEB approval but included for transparency. The plan also includes carryover projects from previous years.
Figure 84 below illustrates the overall change in asset age profile for Downline Reclosers 20 between 2025 and 2026. Date: December 12, 2025 Page 129 of 782 REDACTED REDACTED (CONFIDENTIAL INFORMATION REMOVED) 2026 ACE Plan CONFIDENTIAL (A...
AI summary The text presents figures illustrating the change in the age profile of Downline Reclosers between 2025 and 2026, as part of the 2026 Annual Capital Expenditure (ACE) Plan. It also mentions a figure showing the current state of Padmount Transformer age profiles.
U&U Q2 - August 5, 2025 $ - $ 2,426,669 $ 445,032 Approved Transmission C0074130 Robie Street Underground P&A OTQ - September 9, 2025 $ - $ 4,465,119 $ 1,221,314 Awaiting Approval Generation C0080112 HYD Big Falls Unit 6 Rotor Re-Insulatio...
AI summary The text provides a table listing various projects with their status, costs, and associated dates. These projects include transmission, generation, and general plant initiatives, with some awaiting approval and others already approved. Costs and associated details are provided for each item.
2026 ACE Plan 2026 ACE Plan $ 2,818,855 $ 2,818,855 $ 66,043 Awaiting Approval Transmission C0053234 96H-T1 Transformer Replacement 2026 ACE Plan 2026 ACE Plan $ 2,056,752 $ 2,056,752 $ 21,093 Awaiting Approval Generation C0068888 TUC3 Con...
AI summary The text presents a list of capital expenditure items under the 2026 ACE Plan, including transformer replacements, system upgrades, and switch replacements, with associated costs and approval status.
ACE Plan Reference Submission or Status Category CI Number Title Submission/Date ACE Amount Actual Spend FIN Submission Date FIN Amount Variance (or U&U and P&A) Approved Amount Awaiting Approval Transmission C0070909 70W-T52 Transformer A...
AI summary The document presents a table outlining several capital items (CIs) under the 2026 ACE Plan, including their status, category, CI numbers, titles, submission dates, ACE amounts, actual spend, and variance. These items are related to infrastructure upgrades in transmission and distribution systems.
on C0080110 L7012 Replacements and Upgrades Phase 1 2026 ACE Plan 2026 ACE Plan $ 5,370,318 $ 5,370,318 $ - Awaiting Approval General Plant C0080111 2026 RTU Deployment 2026 ACE Plan 2026 ACE Plan $ 8,322,655 $ 8,322,655 $ - Awaiting Appro...
AI summary The text presents a list of capital expenditure items under the 2026 ACE Plan, including replacements, upgrades, and refurbishments across various projects, with associated costs listed for each item.
C0080206 POA Boiler Refurbishment 2026 2026 ACE Plan 2026 ACE Plan $ 1,304,600 $ 1,304,600 $ - Awaiting Approval General Plant C0080252 Intelligent Asset Data Capture & Integration Platform 2026 ACE Plan 2026 ACE Plan $ 267,941 $ 267,941 $...
AI summary The text lists several capital expenditure projects under the 2026 ACE Plan, including boiler refurbishments, asset data integration platforms, distribution right of way expansions, and various hydroelectric refurbishment and analysis projects. Some are awaiting approval, while others are pending submission.
02 Sydney Depot Improvements 2026 ACE Plan (for Subsequent Approval) $ 2,700,000 $ - Pending Submission Transmission C0032382 142H - Susie Lake Substation 2026 ACE Plan (for Subsequent Approval) $ 8,256,386 $ 671,904 Pending Submission Gen...
AI summary The document lists several capital expenditure items under the 2026 ACE Plan, including improvements to the Sydney Depot, Susie Lake Substation, and various IT and generation-related projects, with associated costs and approvals pending.
HYD ANN Facility Isolation 2026 ACE Plan (for Subsequent Approval) $ 4,083,925 $ 2,778,287 Pending Submission Transmission C0059483 83V L-5017 and L-5046 Rebuild Tap 2026 ACE Plan (for Subsequent Approval) $ 1,207,318 $ 212,714 Pending Sub...
AI summary The document outlines several capital expenditure projects under the 2026 ACE Plan, including facility isolation, transmission rebuilds, IT migrations, and environmental upgrades, with varying amounts approved and pending.
IT - Managed Detect & Respond 2026 ACE Plan (for Subsequent Approval) $ 2,585,071 $ 140,002 Pending Submission General Plant C0068714 IT - Identity & Access Management 2026 ACE Plan (for Subsequent Approval) $ 4,324,589 $ 914,563 Pending S...
AI summary The text lists several IT and transmission projects with associated costs under the 2026 ACE Plan (for Subsequent Approval), including IT security, DERMS solutions, ADMS upgrades, and transformer replacements.
10H-T2 Transformer Replacement 2026 ACE Plan (for Subsequent Approval) $ 2,878,891 $ 20,582 Pending Submission Transmission C0070327 IR 673 Network Upgrade Benjamins Mill Wind 2026 ACE Plan (for Subsequent Approval) $ 265,000 $ 7,946 Pendi...
AI summary The text lists various capital expenditure projects under the 2026 ACE Plan, including transformer replacements, network upgrades, and the construction of a new substation, with associated costs and approvals pending.
HYD Malay Falls Rubber Dam 2026 ACE Plan (for Subsequent Approval) $ 2,237,339 $ 42,684 Pending Submission Generation C0076273 Bear Head Ash Management Site - Life Extension 2026 ACE Plan (for Subsequent Approval) $ 10,148,108 $ 18,725 Pen...
AI summary The document outlines several pending submissions related to capital expenditures under the 2026 ACE Plan, including projects such as the Malay Falls Rubber Dam, Bear Head Ash Management Site life extension, and various infrastructure upgrades across generation, distribution, and transmission systems.
Replacements and Upgrades Phase 1 2026 ACE Plan (for Subsequent Approval) $ 2,490,532 $ - Pending Submission Generation C0080219 HYD Deep Brook Spillway & Intake Refurbishment 2026 ACE Plan (for Subsequent Approval) $ 3,142,201 $ 4,250 Pen...
AI summary This text outlines various capital expenditure projects under the 2026 ACE Plan, including turbine refurbishments, infrastructure upgrades, and other initiatives, with associated costs and pending approvals.
se 2 2026 ACE Plan (for Subsequent Approval) $ 13,000,000 $ 2,875,292 Pending Submission General Plant C0082133 IT - Renew Microsoft Enterprise Agreement 2026 ACE Plan (for Subsequent Approval) $ 1,800,000 $ - Pending Submission Generation...
AI summary The text outlines the 2026 ACE Plan (for Subsequent Approval) with specific line items related to IT and generation capacity requirements, along with deferred or cancelled projects from the 2025 ACE Plan. These projects are part of broader planning and capital expenditure processes.
2026 ACE Plan Appendix D Page 7 of 179 New Updates - Scope Change • Examples that would trigger a Scope Change application: o The refurbishment (component replacement) of an asset is changed to a full asset replacement. (i.e. a Steam Turbi...
AI summary This section outlines the conditions under which a scope change would be required for the 2026 ACE Plan. Examples include changing from component replacement to full asset replacement or altering the technology application. However, changes in quantity of units without altering the project intent are not considered scope changes.
conducted since the filing of the 2025 ACE Plan related to evaluating 26 and costing the MHS decommissioning and partial decommissioning options. 27 28 10. The Board directs NS Power to include cost estimates for further preliminary 29 eng...
AI summary The Nova Scotia Energy Board (NSEB) directs Nova Scotia Power Inc. (NS Power) to include detailed cost estimates for Mersey system updates in its 2026 ACE Plan, including preliminary engineering, stakeholder engagement, environmental studies, and procurement costs. These estimates must also be incorporated into NS Power’s NPV analysis comparing the Mersey Redevelopment Project to decommissioning options.
1 Extension Period). As such, E1’s prior five-year DSM Plan development was temporarily paused 2 while E1 prepared and filed its 2026 DSM Plan Extension Application, which remains an open 3 Matter before the Board. 43 E1’s 2026 DSM Plan ta...
AI summary E1's 2026 DSM Plan extension targets 528.7 GWh energy savings and 16.3 MW DR capacity with $236.8M investment. NS Power collaborates with DSMAG on cost-effectiveness frameworks and electrification strategies, focusing on affordability and peak load reduction through hybrid electrification scenarios.